Julius Berger Nigeria Plc has released fresh images and report on the progress recorded with the ongoing construction of the 2nd Niger Bridge.
The company was awarded the contract in July 2018 by President Muhammadu Buhari with work commencing in September 2018 with a projected contract period of 3 and a half years.
In a fresh report which accompanied the images, the company said as of January 10, 2020, the project had reached a stage of 30.12% completion.
The project is expected to be completed by February 2022. In June, the company launched a website to “allow Nigerians track the status” of the project.
Below are the newly released report and pictures:
Olakunle Churchill, the ex-husband of Nollywood actress Tonto Dikeh, said there is no legally recognised…
Following the widespread circulation of the Eniola Sisialagbo video, the social media personality has issued…
Eniola Sisialagbo has become a major topic of discussion across social media platforms following the…
Senegalese-American singer, Akon has admitted that he once found life simpler when he was involved…
The Delta State Police Command has confirmed that the officer seen in a viral video…
Nigerian businessman Pascal Okechukwu, popularly known as Cubana Chief Priest, has announced his bid to…