LAGOS, Nigeria — Eko Electricity Distribution Company recorded the highest metering rate among Nigeria’s 11 electricity distribution companies in October 2026, at 91.68%, as the national count of metered customers reached 8.35 million.
The Nigerian Electricity Regulatory Commission’s factsheet on the metering status of distribution companies for September and October 2026 shows that Eko had 695,661 active customers in October, of whom 637,786 were metered. The company added 6,814 newly metered customers during the month.
Ikeja Electricity Distribution Company followed with a metering rate of 88.37%, and Abuja Electricity Distribution Company ranked third at 83.24%. Ikeja had 1,203,770 metered customers and Abuja 1,206,559.
Port Harcourt Electricity Distribution Company recorded 72.49%, with 822,477 of its 1,134,605 active customers metered. Benin Electricity Distribution Company recorded 66.02%, and Ibadan Electricity Distribution Company 61.87%. Ibadan added 47,814 meters in October, the highest number among the distribution companies. Enugu Electricity Distribution Company recorded 53.08% and Kaduna Electricity Distribution Company 44.71%.
The three lowest rates were recorded by Jos, Yola and Kano distribution companies, at 40.34%, 41.02% and 43.71% respectively.
Nationally, Nigeria had 12,912,114 active electricity customers in October, up from 12,827,789 in September. The number of metered customers rose from 8,208,020 to 8,352,714, lifting the national metering rate to 64.69% from 63.99%. Newly metered customers, however, fell from 162,455 in September to 144,694 in October.
About 4.56 million active customers remain unmetered, representing 35.31% of the national customer base. The Nigerian Electricity Regulatory Commission defines active customers as those billed or who bought electricity at least once in a 12-month period.
In November 2026, the Commission approved ₦30 billion for the third tranche of the Meter Acquisition Fund, to provide free meters to unmetered Band A customers and accelerate metering for Band B customers. The programme requires all installations to be completed by May 31, 2027.
The Federal Government had installed 707,765 meters across the country in the first half of 2026, a 71% increase on the 412,792 installed in the same period of 2025. Under the first phase of the $500 million World Bank-financed Distribution Sector Recovery Programme, 668,000 meters had been installed by August 2026, 60% of the 1.033 million meters delivered under the programme. In July 2026, the government announced plans to deploy 1.56 million meters before the end of the year after resolving a dispute with local meter manufacturers.