Gombe substation capacity doubles with new transformer

Gombe substation capacity doubles with new transformer

GOMBE, Gombe State, Nigeria — The Federal Government has doubled the electricity transmission capacity of the Gombe Transmission Substation, from 300 megavolt-amperes to 600 megavolt-amperes, after installing a new 300 megavolt-ampere transformer.

The Transmission Company of Nigeria disclosed the upgrade in a statement issued on Thursday, November 19, 2026. The Minister of Power, Engineer Joseph Olasunkanmi Tegbe, commissioned the two transformers at the 330/132/33 kilovolt substation.

Before the upgrade, the substation had an upstream capacity of 300 megavolt-amperes, supported by two 150 megavolt-ampere transformers, and a downstream capacity of 150 megavolt-amperes. The new 300 megavolt-ampere, 330/132 kilovolt transformer raised upstream capacity to 600 megavolt-amperes, equivalent to 480 megawatts.

The project also replaced an existing 30 megavolt-ampere unit with a 100 megavolt-ampere, 132/33 kilovolt transformer, increasing downstream capacity to 220 megavolt-amperes, equivalent to 176 megawatts.

Tegbe said rising electricity demand had placed pressure on the substation’s existing capacity. He described it as a strategic transmission hub serving Gombe and neighbouring states, including Yobe, Borno and Adamawa, and said the upgrade would ease the operational constraints that had affected it.

The Managing Director and Chief Executive Officer of the Transmission Company of Nigeria, Sule Ahmed Abdulaziz, said the company awarded the contract to ISIN Electromechanical Industries Limited in June 2021, and that the project was completed in June 2026. He said replacing transformers at a working transmission station required careful coordination to keep electricity flowing while existing equipment was removed.

Abdulaziz said the upgraded transformers would give the station more operational flexibility and allow it to transmit more electricity through the 330 kilovolt network. The project is also expected to increase the capacity of the Jos Electricity Distribution Company to receive power for distribution to customers in Gombe.

The upgrade comes as the Federal Government works to address constraints across the national grid. The Minister has previously identified overstretched transmission infrastructure, gas supply constraints, distribution losses and accumulated industry liabilities as major challenges. He attributed recent supply disruptions in parts of the country to generation and transmission constraints, including planned maintenance at the Egbin Power Station, gas shortages and damage to critical transmission lines.

In 2024, the Transmission Company of Nigeria commissioned 48 transformer projects across the country, adding 4,928 megavolt-amperes to the national transmission network.